Question from Procurement
Submitted by bridge on Sat, 06/29/2013 - 02:14
Forums:
You are reviewing the procurement statement of work for a fixed price road construction contract. You notice that there is a much larger number of bulldozers called out in the contract than have been in use on the project. When questioned about it, the vendor says that the additional bulldozers were added as reserve because the scope of work was not complete when the contract was signed. Who is at fault?
A. The procurement team
B. No one