difference between BAC and PMB
Submitted by abdsal on Fri, 05/03/2013 - 19:30
Forums:
Dear all ,
Kindly clear my doubt.
I had a mock exam question.
A railroad construction project is under execution. The project manager is using Earned value Technique to measure the project performance. The total planned value of the project is known as:
A. Performance measurement baseline
B.Earned Value
C. Budget at completion
D. Estimate at Completion.