difference between BAC and PMB

 

Dear all ,

 

Kindly clear my doubt.

 

I had a mock exam question.

 

A railroad construction project is under execution. The project manager is using Earned value Technique  to measure the project performance. The  total planned value of the project is known as:

A. Performance measurement baseline

B.Earned Value

C. Budget at completion

D. Estimate at Completion.

 

my answer was A but the key gave choice C Budget at completion.