Time Management Question

 Q: The project is calculated to be completed in 4 days after the desired completion date. You do not have access to additional resources. The project is low risk, the BCR is expected to be 1.6, and the dependencies are preferential. Under these circumstances, what would be the next BEST thing to do?

 

A. Cut resources from activity

B. Make more activities concurrent

C. Move resources from preferential dependencies to external dependencies

D. Remove an activity

 