Someone please help me on this network diagram concept:
Submitted by AD on Sun, 03/31/2013 - 18:25
Forums:
Someone please help me on this network diagram concept:
While developing network diagram HeadFirst book adds 1 day while moving forward from one activity to other
so, ES of B = LS of A + 1. Subtraction happens on backward
Rita assumes ES of B = LS of A.
I always make wrong answer to these questions when it should be an easy catch.
Thanks in advance,
AD