Closure question..D or A with expln
Submitted by anand2381 on Mon, 02/25/2013 - 13:29
Forums:
Question: A project manager is in the final closure phase of the project . Which of
the following should he do FIRST as part of the project closure activity?
Options:
A. Get formal sign off from the customer to confirm customer acceptance of final
deliverable
B. Measure customer satisfaction as a key performance indicator of project's success
C. Hand off completed project deliverables to operations and management
D. Measure project scope against project management plan