Confused with diff formulas for EAC and ETC
Submitted by Sree on Mon, 02/25/2013 - 10:17
Forums:
Hi All ,
Im aware that for finding Estimate at completion i have 4 diff formula
** EAC ***
1. EAC = BAC \ CPI : no veriances
2. EAC = AC - ETC : Original Estimates were flawned
3. EAC = AC+(BAC-EV) : ATYPICAL
4. EAC = AC+(BAC-EV)/CPI : TYPICAL
** ETC ***
1. ETC = EAC-AC
2. ETC = BAC-EV :- TYPICAL
3. ETC = BAC-EV / CPI :- ATYPICAL