Headfirst 200 Questions - Question on Critical Path
Submitted by sashsarv on Wed, 12/26/2012 - 23:52
Forums:
Hello
I attempted the Headfirst 200 this morning, and I had doubts on this question
There was a sequence diagram given, and then LF was asked to be calculated for one of the activities that had path convergence.
The answer for the question was below:
It’s just easy to calculate the late finish (LF) of an activity in a network diagram. Look at the