When a negative risk occurs in a project, a response to it would be called
Submitted by agoyal2 on Mon, 12/24/2012 - 20:30
Forums:
The below question is from Christopher Scordo book. I selected the answer as A since there is nothing in the question that indicates that the risk was not planned. The book however mentions that the correct answer will be 'C'.
Your thoughts?