A Questions on chapter Cost Management
Submitted by oberoi.amit@out... on Sat, 05/10/2014 - 18:49
Forums:
Hello everybody here,
I got 2 quetion here first is of simple maths, however i am not able to accept the answer mentioned in the Andy Crowe book.
1 Question is :
We have EV = 127253, BAC = 275,000 and SPI =0.77
We need to calculate how much work was expected to have been completed at this point.
I think it is asking for PV here..
Can any body help me understanding the caculation to caculate PV here.
2 Question
What is Parametric Modelling? Can anybody elaborate?
Thanks in advance.