What number tells you the difference between the amount of money you planned on spending and what you`ve actually spent so far on the project?

A. AC

B. SV

C. CV

D. VAC

It should be C

cnppmp1's picture

It should be SV, as it is talking about planned value and other value should be consdiered as EV is actually accomplished value.

Regards

CN Patil