 1) Administrative closure

2) Project Archives

3) release of resources

4) Lessons learned

5) Formal acceptance of resources

6) Final status report

7) Transfer of project deliverables

 

What is the order ( i did not put them in correct order above intentionally) as per PMI.. I think if we know the correct order and logic, i think no one will be able to score less than 14-15 questions in closing..

 

Which comes first and what follows .. Please provide some explaination on this

 

 

============

 

 

 

 I had the same question. Refer to this link it helped me clarify the process 

http://www.deepfriedbrainproject.com/2010/04/pmp-order-activities-closing-process.html

Here is the ORDER for Project closure:



  1. Confirm work is done to the requirements

  2. Complete Procurement Closure

  3. Gain Formal acceptance of the product

  4. Complete final performance reporting

  5. Index & Archive records

  6. Update lessons learned knowledge base

  7. Hand off completed product

  8. Release Resources

 


Regards,


RD

admin's picture

From zephyr's link I guess the order of closing process in PMP would be clear to you. From the list you sent. It would be

 

 

7) Transfer of project deliverables

6) Final status report

5) Formal acceptance of resources

4) Lessons learned

2) Project Archives

3) release of resources

1) Administrative closure ( Done once per project phase or for entire project , This terminology was there in 3rd edition now its under close project. )