cost management -- cost variance

 Julie has just completed a periodic analysis of her project. Her estimate to complete(ETC)  the project is an additional $280,000. This brings the estimated total cost (EAC) of the project to $600,000. If Julie calculates Earned Value (EV) to be $350,000, what is the cost variance (CV) on this project?

Ans is given as $30,000

CV= EV-AC

ETC=EAC-AC

Getting confused in calculating AC

If BAC = EAC*CPI i.e., BAC = EAC *EV/AC is to be considered, then is BAC = 600,000-280,000 = 320,000?

 

Iam not knwing as to how AC is to be arrived at?

can someone guide please?

The case above is mentioned is of atypical phenomenon


in such case


EAC = AC + BAC -EV


EAc = 600000


ETC = 280000 which is eqvivalent = BAC - EV


BAC = 280000+EV(350000) = 6300000


Cost Variance = EAC - BAC =600000-6300000 = -30000


I hope i am correct


Bhavesh

 How is it atypical? Can you please elaborate?

Regards

Vijaya

 This brings the estimated total cost (EAC) of the project to $600,000.

Her estimate to complete(ETC)  the project is an additional $280,000.

EAC = AC +ETC

600000 =AC + 280000

AC = 320000

CV = EV-AC

If Julie calculates Earned Value (EV) to be $350,000,

CV = 350000-320000 = 30000

 Thank You SIr

Cost variance = +30,000