C) Project Management Plan
D)Change control plan
rwmv
Wed, 05/15/2013 - 12:55
Permalink
It should be documented in Change control system
crushPMP
Wed, 05/15/2013 - 12:56
D?
vijayavadrevu
Wed, 05/15/2013 - 14:34
I too have answered as D, but in the key it is given as C. Iam not clear
nevish
Wed, 05/15/2013 - 15:09
i would say D as well....please can anyone kindly clarify.
thanks
Vishal
Geethika
Wed, 05/15/2013 - 15:48
silly, but may be the catch
C) Project Management Plan (Ans: Change management plan contained within)
D) Change control plan (made up term)
bkthakkar
Wed, 05/15/2013 - 15:55
agree with PMP
Wed, 05/15/2013 - 16:10
Thank You !!!
rwmv
Wed, 05/15/2013 - 12:55
Permalink
Ans -C
It should be documented in Change control system
crushPMP
Wed, 05/15/2013 - 12:56
Permalink
D?
D?
vijayavadrevu
Wed, 05/15/2013 - 14:34
Permalink
I too have answered as D,
I too have answered as D, but in the key it is given as C. Iam not clear
nevish
Wed, 05/15/2013 - 15:09
Permalink
answer
i would say D as well....please can anyone kindly clarify.
thanks
Vishal
Geethika
Wed, 05/15/2013 - 15:48
Permalink
C
silly, but may be the catch
C) Project Management Plan (Ans: Change management plan contained within)
D) Change control plan (made up term)
bkthakkar
Wed, 05/15/2013 - 15:55
Permalink
agree with PMP
agree with PMP
vijayavadrevu
Wed, 05/15/2013 - 16:10
Permalink
Thank You !!!
Thank You !!!