change control system

C) Project Management Plan

D)Change control plan

It should be documented in Change control system

crushPMP's picture

 D?

 I too have answered as D, but in the key it is given as C. Iam not clear

i would say D as well....please can anyone kindly clarify.

 

thanks

 

Vishal

silly, but may be the catch

C) Project Management Plan (Ans: Change management plan contained within)

D) Change control plan (made up term)

agree with PMP