Question

 Which of these is not an approved Estimate Activity Durations technique?

  1. Three Point Estimating

  2. Parametric Estimating

  3. Analogous Estimating

  4. Critical Path Estimation

Critical Path Estimation,(D)

cnppmp1's picture

D

Regards

CN Patil

jvleminc's picture

Doesn't exist, made up term.