Question
Submitted by Vishwanath on Wed, 07/10/2013 - 10:35
Which of these is not an approved Estimate Activity Durations technique?
-
Three Point Estimating
-
Parametric Estimating
-
Analogous Estimating
-
Critical Path Estimation
Forums:


bkthakkar
Wed, 07/10/2013 - 11:27
Permalink
Critical Path Estimation,(D)
Critical Path Estimation,(D)
cnppmp1
Wed, 07/10/2013 - 15:38
Permalink
D
D
Regards
CN Patil
jvleminc
Wed, 07/10/2013 - 19:04
Permalink
D
Doesn't exist, made up term.