resource levelling

In which of the following scenarios, resource leveling is not applicable?

 
A. When the requisitioning cost of the resource is high and the usage need is
intermittent
B. As a result of initial Project scheduling, the work needs to be performed by a resource
A in a day works out to 10 hours, when he is scheduled to work only for 8 hours
C. When the Project Manager wants to keep the Project timelines under control
D. When a critical resource has to multiplex between multiple Project

 Think it is B

Yes. Absolutely B.

 answer is C

Need admin help and support:)

 The answer is C.  Because, resource leveling generally extends the timelines.  In this case, the PM wants to keep the project timelines under control.

The answer is not B because in the case of choice B, the resource is overloaded.  Hence, it needs leveling.

Answer A and D are also not correct, because in A the resource is intermittently used.  So, it should be leveled.  In D, the resource is working on multiple projects and so, there is a good possibility of resource being overloaded.

I read the Question Wrong. Hence Sorry.

It is C. I read it as Resource Levelling applicable.