Time management: Lag and Buffer
Submitted by al.zo on Thu, 03/21/2013 - 13:55
Forums:
Hi Experts,
I met the following question:
If a project manager wants to schedule a delay between activities in a project plan, he/she uses:
a. Float
b. Lag
c. Buffer
d. Lead
I answered b. but the solution showed c. as correct answer.
Is it really correct?