Time Management Questions
Submitted by san on Thu, 03/21/2013 - 06:32
Forums:
1)An activity has an early start (ES) of day 3 , LS of day 13 ,EF of 9 and LFof 19 . What is the duration of the activity
1)3
2)6
3)7
4)10
Please provide the answer with explantion