87. A project was assessed and the following Earned value data have been found: PV: $750,000 EV: $750,000 AC: $900,000 What is the Burn rate of the project?
Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.
87. A project was assessed and the following Earned value data have been found: PV: $750,000 EV: $750,000 AC: $900,000 What is the Burn rate of the project?