PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

pmp ques bank ques


 


53. What is the expected value of the number of days to complete the project?
a. 47.3
b. 22.0
c. 32.3
d. 48


 


54. It is desirable to make an estimate that has a greater than 95% chance of being correct. Which of the following ranges of time for the impletion of the project best describes this probability of being correct?