The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:
------------------------------
Which of the following processes is not a part of Project Communications Management?
A) Plan Communications
B) Distribute Information
C) Identify Stakeholders
D) Control Communications
------------------------------