PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Calculate Estimated cost while SV and CV are given

 The schedule variance for a project is 20%.The Budget for the project is $480,000. What is the estimated cost on project completion if the EV and AC of the project currently is $48,000 and $60,000 respectively and if the current cost variance and schedule variance is expected to continue in future?