Help! really confused with change control process.
Submitted by xiaou24 on Sat, 05/15/2010 - 23:59
Forums:
I did the head first pmp test, and got several answers wrong about change control process, my question is -- Should we documented the change request first or should we evaluate its impact first?
Before I thought document change request went first then its impact was evaluated, but according to headfirst answers, evaluate impact goes first. I am really confused.
here is the question, I answered A, headfirst answer is C.