Questiona that need explanation/Justification
Submitted by badhrig on Mon, 05/17/2010 - 10:06
Forums:
Question 1 :
You are managing the changes made to the scope baseline. The causes of variances and the reasoning behind the corrective action chosen should be included in:
Choice 1 Recommended corrective action
Choice 2 Project management plan
Choice 3 Scope management plan
Choice 4 Organizational process assets updates
Question 2: