Question 1 :


You are managing the changes made to the scope baseline. The causes of variances and the reasoning behind the corrective action chosen should be included in:


 
 
  Choice 1  Recommended corrective action 
 
  Choice 2  Project management plan 
 
  Choice 3  Scope management plan 
 
  Choice 4  Organizational process assets updates
 