Critical Path Method Question
Submitted by philzs on Mon, 02/09/2015 - 13:25
Forums:
Guys,
I saw two different kind of graphic ofr CPM.
Type 1
One type ( from Rita book ) by example, where you the time is associated with an activity.
Example :
Activity A Duration is 2 days.
this type is easy to understand and easy to calculate Forward / Backward Path
Type 2
Another Type that I saw in PMStudy, where The time is actually not associated to the Activity but "Between The Activity"
Example :