Control Procurement - How to manage schedule
Guys,
Input of control procurement are
Project Document
Project Management Plan
Agreement
Approved change request
Work performance report
Work performance Data
How can we compare the result to a Schedule Baseline, if we took work performance Data we have the "Actual" (where we are now) but where is the baseline in those input, If I read PMBok, when it describe Project Document and Project Management plan it doesnt talk about any plan schedule...