Project Risk Question
Submitted by YogSam on Tue, 02/03/2015 - 00:34
Forums:
The Risk Management plan will usually contain the definitions of risk probability and impact.
Which of the following has the highest impact (negative) on a project?
A rating of 1.1 on the impact scale
A rating of 0.8 on the impact scale
A rating of 0 on the impact scale
A rating of 0.1 on the impact scale