Questions about Project Management Process Groups (from Rita's book)
Submitted by yummydoves on Sat, 09/21/2013 - 11:58
Forums:
Hi, I just did Project Management Scramble in chapter 3 of the book and did a few questions wrong. Would someone help to explain why they are wrong? Many thanks!
1. Action: Calculate estimate to complete
Which process group: Should be Monitoring & Controlling, but I chose Planning
2. Action: Increase effectiveness of processes
Which process group: Should be Executing, but I chose Monitoring & Controlling
3. Action: Reanalyze existing risks