Question from Project time managemnt
Submitted by ROOPESH.SHAR on Thu, 09/19/2013 - 12:49
Forums:
Q- A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of -
a- Finish - to - Start
b - Start - to - Finish
c- Start - to - Start
d - Finish - to - Finish
Please suggest the answer with clarification.