Question about changes

Question:

You are completing the work defined in the project scope statement of a new software development project when a team member points out that you have an opportunity to deliver enhanced capability to the client at no extra cost, time, or risk to the project.

What should you do next?


Choices:

A. Assess the change through the change control process and, if approved, amend the project scope statement.

B. Decline to make the changes and proceed to deliver exactly what the scope statement sets out.