resource levelling
Submitted by agera on Thu, 08/29/2013 - 13:54
Forums:
In which of the following scenarios, resource leveling is not applicable?
A. When the requisitioning cost of the resource is high and the usage need is
intermittent
B. As a result of initial Project scheduling, the work needs to be performed by a resource
A in a day works out to 10 hours, when he is scheduled to work only for 8 hours
C. When the Project Manager wants to keep the Project timelines under control
D. When a critical resource has to multiplex between multiple Project