Need Clarification.
Submitted by Sundara.damaraj... on Mon, 05/12/2014 - 03:18
Forums:
You are managing the implementation of ERP software in a factory. Software support must be provided round the clock. You need to schedule the shifts of the crew in such a way that a crew cannot finish their shift until next shift crew has arrived. What type of dependency exists between the shifts?
I have answered as "Finish to Start".
My justification :- Predecessor is "First Crew" Successor is "Next shift Crew"
But the correct answer is "Start to Finish"
Can someone explain this ?