What should you do first?
1. Your manager gives you a project charter and asks you to begin work immediately and to provide her with a schedule. What should you do first?
a) Begin estimating the activities necessary to complete the scope of work.
b) Begin creating a Project Scope Statement.
c) Create an activity list and then begin to assign the activities to resources.
d) Identify a team and obtain approval for their participation from their functional
Please let us know why u chose that particular answer choice?