compress the schedule
Submitted by Jp2786 on Tue, 05/27/2014 - 02:56
Forums:
The sponsor of the project you are managing asks you to compress the schedule.
Which of the following CORRECT?
A crashing always shorten the timeline but often increases risk
B fast tracking often results in increased cost
C crashing is only a viable alternative if earned value analysis indicates that the project is ahead of schedule and under budget
D fast tracking will result in less parallel activities than crashing project
*****