What is the duration of this activity?
Submitted by Jp2786 on Tue, 05/27/2014 - 03:18
Forums:
1. An activity has an early start,(ES) of day 13,an early finish (EF) of day 9 and a late finish (LF) of day 19. What is the duration of this activity?
A 3
B 6
C 7
D 10
I'm guessing there is typo in the question how can ES be 13 and EF be only 9?