To whom is the project manager MOST accountable?

  Senior management has imposed a project delivery date prior to the acceptance of

project scope statement. To whom is the project manager MOST accountable?

a) Project sponsor

b) Project team

c) Customer

d) Senior Management

 

Pls let us know the rational for chossing a particular answer? 