To whom is the project manager MOST accountable?
Submitted by Jp2786 on Tue, 05/27/2014 - 02:33
Forums:
Senior management has imposed a project delivery date prior to the acceptance of
project scope statement. To whom is the project manager MOST accountable?
a) Project sponsor
b) Project team
c) Customer
d) Senior Management
Pls let us know the rational for chossing a particular answer?