WBS
The process of creating a work breakdown structure most likely results in which of the following?
A. Project schedule
B. Team buy-in
C. Project budget
D. List of identified risks
I selected B, which was the correct answer too. However, this conflicts with a similar question as below -
Which best explains why WBS is important to a project?
A. It provides a hierarchical diagram of the project
B. It makes it easier to estimate activities, costs & resources