The stakeholders’ have most influence on a project during?

PMP Fighter's picture

The question:

The stakeholders’ have most influence on a project during : 

A. During the planning phase.

B. In the beginning of the project.

C. Throughout the project.

D. During the execution phase.

I choose C, but the answer is B.

The mock exam provider explanation :

Stakeholders' influences are at the peak in the beginning of the project.