Critical Path and Near Critical Path
Submitted by interservicio on Mon, 03/31/2014 - 08:05
Forums:
Imagine you have a critical path A-B-C-D of 20 days duration.
You have other path like A-B-E of 16 days duration.
Now the questions tells you that activity E increases in 3 days.
What's the situation now?.
Possible answers:
a) Nothing
b) Risk increases
Sumarized, answer B is correct.
I realize that A-B-E has become a near-critical-path (19 days). But is it enough to consider that the risk of the project has increased ??