subsequent costs?
Submitted by PMP Fighter on Thu, 04/03/2014 - 02:34
Forums:
Following project data are given to you
a) Target price = $90000
b) Ceiling price = $100000
c) Customer's share of cost overruns = 70%
d) Target cost = $80000
You are requested to and out point at which the seller will assume all subsequent costs:
A $ 104286
B $ 80000
C $ 14286
D $ 94280